# How Long Does Foundation Repair Take? (Days, Not Weeks)

5 min read · Updated July 2026 · By Ricardo Chamorro · ICC-certified Residential Building Contractor

TYPICAL CENTRAL TEXAS TIMELINES · THE QUOTE INCLUDES YOURS

Settled corner (slab, 4–6 piers)

1–2 days

Full side (slab, 8–12 piers)

2–3 days

Pier & beam crawlspace re-level

1–2 days

Combined scopes / full perimeter

3+ days

The lift itself is usually an afternoon. Excavation and pier installation are what fill the days.

Foundation repair is measured in days, not weeks. And the part people dread, the lift, is the shortest part.

How long does foundation repair take? For most Central Texas homes, **one to three days**, and the part homeowners dread most, the lift itself, is usually the shortest part of the schedule. The dig is the job; the lift is the afternoon. Here's how the days actually break down, what can stretch them, and what your house feels like while it happens.

A pier installation in progress. Excavation and pier work fill most of a 1–3 day repair.

## Typical timelines by job type

**A settled corner on a slab** (the most common repair, typically 4–6 piers) usually runs **1–2 days**: pits opened and piers pressed to depth on day one, the staged lift and backfill finishing on day one or two. **A full side** (8–12 piers) runs **2–3 days** for the same sequence with more holes. **[Pier-and-beam](https://motmotfoundationrepair.com/pier-beam-foundation-repair/) crawlspace work** (shims, blocks, beam and sill repairs) most often finishes in **1–2 days**, because nothing gets excavated; the crew works under the house, not around it. Larger beam replacements and combined scopes (crawlspace work plus a settled grade beam) run longer, and your quote includes the schedule so there's no mystery. The full sequence (what happens in what order, and why) lives on our [process page](https://motmotfoundationrepair.com/foundation-repair-process/).

Morning of day one: pits open at the marked pier locations while the household goes about its day.

## Where the time actually goes

Excavation and pier installation fill most of the clock: each pit is opened, each pier is pressed hydraulically until the soil proves it's carrying the load, and each one is logged with its depth and pressure. The lift is the finale: hydraulic rams raising the settled section in small increments, with elevation readings re-shot between stages. It's typically **an afternoon**, and it's the good part: [doors that stuck for years](https://motmotfoundationrepair.com/blog/why-doors-stick-foundation/) start latching before the crew packs up.

The hydraulic work (pressing piers to depth, then lifting in measured stages) is hours, not days.

## What stretches a timeline

- **Scope.** More piers, more days. A full-perimeter run is a different week than a two-pier corner, one more reason [catching movement early](https://motmotfoundationrepair.com/early-foundation-repair-can-save-money/) pays.
- **Access.** Interior piers reached through access pits, tight side yards, and hand-dug pits in rocky soil all add hours.
- **Weather.** Heavy rain can pause excavation. Clay pits and wet spoil don't mix. Crews resume as soon as the ground allows.
- **Paperwork.** Permits and engineer's letters, where required, add lead time before day one. Those are calendar days, not workdays.
- **Surprises underground.** An undiscovered plumbing leak is the big one: if the inspection pattern points at water, the plumber goes first, and that's a schedule change worth making.

Raked even with the walk so water runs away from the building.

## What repair days feel like from inside

You can almost always stay home: water and power stay on, the noise is digging and occasional hammering rather than demolition, and the crew needs interior access only for elevation checks that take minutes. We wrote a whole piece on exactly this: [can you live in the home during foundation repair?](https://motmotfoundationrepair.com/blog/live-in-home-during-foundation-repair/) Short version, yes, and it covers the few real exceptions. Before the crew arrives, our guide on [how to prepare for foundation repair](https://motmotfoundationrepair.com/preparing-your-home-for-foundation-repair-work/) covers the little things that make day one smoother: moving fragile items off shelves near the work, flagging sprinkler lines, clearing the perimeter.

Several holes are open at once along this wall, which is how most of a repair day goes.

## The part that takes years, in a good way

The repair takes days; what it buys should last decades. Piers pressed to load-bearing soil are built to outlast the drought cycles that caused the movement ([here's the durability story](https://motmotfoundationrepair.com/how-long-does-foundation-repair-last/)), and the job ends with the paperwork that proves it: before-and-after elevation maps, the pier log, and a [lifetime transferable warranty](https://motmotfoundationrepair.com/lifetime-warranty/). If you're weighing the disruption against the problem, the disruption is smaller than most people budget for.

Want the timeline for your house, not the average? The free inspection ends with a written scope: pier count, price, and schedule.[Get My Timeline](https://motmotfoundationrepair.com/#inspection-form)

---

Source: https://motmotfoundationrepair.com/blog/how-long-does-foundation-repair-take/
Summary: Most foundation repairs take 1–3 days start to finish. What each job type runs, what stretches a timeline, and what repair day feels like. (210) 816-0034.
Motmot Foundation Repair, San Antonio, Texas. (210) 816-0034. https://motmotfoundationrepair.com/