Learning Center · New Construction

RCLA Rules for Texas Foundation Defect Claims

THE SEQUENCE THAT COMES BEFORE A LAWSUIT

STEP ONE · WRITTEN NOTICE

You put the builder on notice in writing, describing the defect specifically enough that somebody can go look at it. Vague letters buy nothing.

STEP TWO · THEIR INSPECTION

The builder gets a chance to come see what you described. Let them, be there, and have your own floor measurements already in hand.

STEP THREE · THE OFFER

The builder can offer a repair, money, both, or nothing. Turning down an offer later judged reasonable can limit what you recover.

Deadlines hang off every step. Get those from a Texas construction attorney, not from a foundation company.

Notice, then their look, then their offer. The act rewards homeowners who run the steps in order and punishes the ones who skip them.

The Residential Construction Liability Act, the RCLA, is the Texas law that sets the order a homeowner has to follow before suing a builder over a construction defect. The short version runs in three steps. You send the builder written notice describing the problem. The builder gets a chance to come inspect it. The builder gets a chance to offer a repair or a payment. Only after that sequence has played out does a lawsuit belong on the table. Skipping a step is how people lose claims they would otherwise have won.

Read what follows as a plain-language map of that sequence. We measure floors for a living, we do not practice law, nothing here is legal advice, and the deadlines wrapped around every step belong to a Texas construction attorney.

What the RCLA covers

The act governs claims a homeowner brings against a builder or a contractor over defects in residential construction. New construction is the common case, and it is the one most people are in when they go looking for this. Repair and remodel work performed by a residential contractor can fall inside it too. Whether your particular job and your particular contract land under the act is a lawyer question with a real answer, and it is worth an hour of somebody's time before you build a strategy on a guess.

What the act does is force a conversation before a courtroom. The structure makes the reasoning obvious. A builder who is told about a defect and given a fair chance to fix it should get that chance, and a homeowner who gives that chance and gets nothing back should not have lost anything but time. The whole thing runs on a record, and that is the part that overlaps with our work.

Two Motmot technicians photographing and logging cracked brick at the slab line during a foundation inspection
Two technicians photographing and logging cracked brick at the slab line. A defect claim runs on a record like this one, built early.

The written notice comes first

Before a lawsuit, the builder has to receive written notice describing the defect. Two things about that letter matter more than its tone.

The first is specificity. A letter saying the foundation is failing gives a builder nothing to inspect and nothing to price. A letter naming the room whose floor sits low by a measured amount, the month the front door stopped latching, and the window a diagonal crack opened above, describes something a person can walk in and look at. Write what you observe and what has been measured. Leave the legal conclusions to the person you hired for them.

Motmot technicians documenting floor elevations at a home's front door during an inspection
Technicians documenting floor elevations at a front door. Notice that names rooms and measured numbers gives a builder something to inspect.

The second is delivery you can prove. Certified mail with a return receipt costs a few dollars and settles a question that otherwise turns into one person's word against another's. Keep a copy of what you sent and the date it left your hands.

Time limits sit on both sides of that letter, one governing how far ahead of a lawsuit the notice has to land and another governing how long you have to bring the claim at all. Those counts shift with the facts, so get them from an attorney before you rely on any of them.

The builder gets to come look

Once notice is out, the builder has the right to inspect the defect you described. Let them. Refusing that visit is a gift to the other side, and you want it anyway, because it tells you who they send and what they are prepared to say.

Be there for it, and treat the visit itself as part of the record. Note the time they arrived, the name and company of everyone who walked in, which rooms they entered and which ones they never opened, and whether they took any readings of their own or only looked. Photograph what they photograph. Anything said in the house that bears on the claim goes into an email to your builder contact before the day ends, written as a summary and inviting them to correct whatever you got wrong. An uncorrected email sitting in their file is evidence. Your memory of the same sentence is not.

Two Motmot inspectors checking a porch door frame for racking during a foundation inspection
Inspectors checking a porch door frame for racking while elevation data loads. Have your own readings before the builder sends anyone out.

The other thing to have ready before that visit is your own measurement. Our ICC-certified inspectors walk the full footprint taking elevation readings and put where the slab actually sits, to the tenth of an inch, on a dated written report. Crack mapping and a drainage review come with it. The full walkthrough of what a foundation inspection measures is worth reading before you schedule one, and the inspection itself is free. Bringing numbers to a meeting where the other side brought adjectives changes how that meeting goes.

What a repair offer means for your claim

After the inspection, the builder can make a written offer. It might be a repair, it might be money, it might be both. It might also be nothing, and silence carries consequences of its own.

If an offer does arrive, read it as a scope of work rather than as a number. An offer to repair a foundation is a set of promises about method, pier type, pier count, access, warranty, and what happens if the house keeps moving after the crew leaves. Whether that scope solves what the elevations show is a technical question, not a legal one, and it is exactly what a second opinion on a foundation scope is built for. We read somebody else's diagnosis and proposed repair against our own measurements and tell you where the two part ways.

Rejecting an offer is where homeowners get hurt. The act is written to reward reasonable behavior on both sides, so turning down an offer later judged reasonable can limit what a homeowner is able to recover. Reasonable gets decided in hindsight, by people who were never standing in your living room. That is why accepting or rejecting belongs to your attorney and your inspector working together, one reading the language and one reading the house.

Where an independent report fits

Our free inspection is the early, cheap, dated baseline. Get one the week you notice the problem, before the next season moves the evidence and before anybody has a motive to argue about what the house looked like. Measure again a few months later and you own movement over time instead of a snapshot.

ZipLevel elevation reading being recorded during a floor elevation survey
A ZipLevel reading during a floor elevation survey. A dated measurement is what turns a complaint into something a builder has to answer.

A structural engineer's stamped report is a different instrument, heavier and not free, and when a defect claim is heading toward a formal fight that stamp is what carries weight in a room full of lawyers. Which one your situation calls for is laid out in our comparison of a free inspection against a structural engineer's report. The usual order is ours first, because our numbers tell you whether you have anything worth paying an engineer to document.

That cuts both ways often enough to say out loud. About a third of our inspections end with no repair needed. Plenty of people arrive certain the builder ruined their house and leave with a floor reading inside normal range, which is a cheaper answer than any lawsuit was going to be.

What we do and what we stay out of

Our part in a claim like this is measurement and documentation. We shoot elevations, map cracks, look at how water leaves the property, and hand you a dated written record a builder, a mediator, or a judge can read. We will also review a builder's proposed scope against what we measured.

What we will not do is tell you what the act requires in your situation, how long you have, or whether an offer on your kitchen table is reasonable. Those belong to a Texas construction attorney, and one who has actually run these claims is worth the consultation fee even if you never file anything. This page is a map of the sequence, not legal advice.

If the sequence runs all the way out and the repair still lands on you, we do the underpinning too, with steel and hybrid piers, scoped off the same elevations the claim was built on. Whether that bill is actually yours on a house still inside its builder warranty is a separate question with its own answer, and we lay that one out in who pays for foundation problems in a new build. Start with the measurement either way. The inspection that decides whether a repair is needed at all is free.

Builder saying it's normal, and you need something better than an opinion? The free inspection measures your floor and puts a dated baseline in your file before the notice letter goes out.Book a Free Inspection

Straight answers

Related questions.

The Residential Construction Liability Act is the Texas law that sets the order a homeowner has to follow before suing a builder over a construction defect. Written notice to the builder comes first, then the builder's chance to inspect what you described, then the builder's chance to offer a repair or a payment. The act reaches residential construction and repair work, and whether your particular contract falls under it is a question for a Texas construction attorney.
Yes, written notice comes before a lawsuit under the act, and skipping it is one of the cheapest ways to damage a claim you would otherwise have won. Make the letter specific. Describe what you observe and what has been measured, name the rooms and the dates, and send it in a way you can prove, such as certified mail with a return receipt. The timing rules around that notice come from your attorney, not from a foundation company.
Yes, and you should let them. The act gives the builder a chance to come look at the defect you described, and refusing that visit helps nobody but the other side. Be there when they come, photograph what they photograph, write down who came and what they said, and email a short summary the same day. Have your own floor elevation numbers in hand before the visit so the conversation runs on measurements instead of opinions.
It can cost you. The act is built to reward reasonable behavior on both sides, so rejecting an offer that is later judged reasonable can limit what a homeowner recovers. Reasonable gets decided in hindsight by people who were not standing in your living room, which is why accepting or rejecting an offer is a decision to make with your attorney and your inspector together, one reading the language and one reading the house.
Sometimes, and rarely first. Our free inspection gives you measured floor elevations with a date on them, which is what tells you whether the movement is real and whether the claim is worth pursuing. A structural engineer's stamped report is the heavier instrument, and it is what carries weight when a claim heads toward a formal fight. Start with the free measurement, then pay for the engineer if the numbers say you have something. About a third of our inspections end with no repair needed.

Wondering about your own house?

A free elevation survey answers in an hour what an article can only describe, and 'you're fine' is a real possible outcome.

Now booking free inspections in Central Texas.

Free inspection request

Tell us what you're seeing.

We'll call to schedule, usually within one business day. Prefer to talk now? (210) 816-0034.

  • 60–90 minutes on site, including the elevation survey
  • Written summary whether or not repair is needed
  • No-pressure pricing with firm numbers, no same-day-only discounts

Name and phone are all we need. Everything else just helps us come prepared.

By submitting, you agree to our Privacy Policy and Terms, and consent to be contacted by Motmot Foundation Repair by phone or email about your request. Consent to texts is not a condition of purchase. See our SMS Terms.